Upcoming and Current Engineering Needs
%%{init: {"theme": "default", "themeVariables": {
"sectionFontSize": "22px",
"sectionFontWeight": "bold",
"fontFamily": "Arial",
"fontSize": "20px"
}}}%%
gantt
title Engineering Schedule
dateFormat YYYY-MM-DD
axisFormat %m/%d
excludes weekends
todayMarker stroke-width:5px,stroke:#0f0,opacity:0.5
section Scott
Fabs for German Consulate :crit, active, scott1, 2025-05-27, 5d
Follow-up :scott2, after scott1, 2d
section Ed
Fabs for SFO Featurewall :crit, ed1, 2025-05-21, 3d
Steel for Atrium :ed2, after ed1, 3d
section Chris
Global Entry for SFO :crit, chris1, 2025-05-21, 4d
Central Block SFO :chris2, after chris1, 4d
What's happening now:
Ed: Fabs for SFO Featurewall
On Deck: Steel for Atrium
Scott: Fabs for German Consulate
On Deck:
Chris: Global Entry for SFO
On Deck: Finish model of prism panels
On Deck: Central Block SFO
Upcoming needs:
- Stanford GSE North -
(2) Main Entry Canopy - FABs in process
Hoist equipment detail for trellis calculations
- Stanford GSE South
(2) Main Entry Canopy - FABs In process
- Composite wall panel FABs ( Jeff/shop and Gary)
- SFO ITB –
- Shop Drawings - feature wall plus glass rail and full height glass wall with glass door - revised and sent to AWS
ICE box fabs - complete
- Fabs for feature wall - ready for fabs
- Shop Drawings STC55 - submitted
- In Transit Lounge - submittal returned
- Global entry window - revise base shoes
- Central Block
- Baggage screening window, Triage station window, Observation window, Transaction window.
In-Transit lounge wall - revise base shoes
- SSF Wellness-
- Add girt layouts to panel drawings
- Additional items - perforated gutter cover, misc brake shapes, etc…
Return insulation on top of the pony wall. Above the ACM - shown on the Overgaard drawings, and Cement panels. Update membrane at these areas too.
- CCSF-
- SCVMC-
Parapet caps and update title blocks - updated
Performance mock-up
Curb adjustment for parking garage
- Bechtel-
- Emmanuel-
Canopy Fabs - will be done 3/17/2025 (complete)
CW2 Radius Fabs - Horizontal Panel (need field dims)
Blumcraft Radius Fabs - Glass Insert (need field dims)
Interior Metal Panels above doors (ready 4/8/25)
Coping panel updates.
BOK supports - shops and fabs done
Threshold
Entrance Panels
- San Mateo-
Fabs for canopy and gutter at main entry
Fabs for composite at main entry
Fabs for fins at main entry
- Milvia-
- Nothing
- Sadev Windscreen at roof CCD (Mina will work on this)
- German Consulate-
- Storefront Fabs - 2 storefronts - 1 early August and 1 in December - shop drawings updated
- San Quentin-
Building D shop drawing updates done 5/15/25 - tickets Review week of 5/15
Parapet Cap fabs - complete
Saddles - For Building A - 5/6/26
- Saddles for Building B - a ways out
Canopy - done
- Stanford Atrium-
- Door shops? (Pittco will do shops, we will review internally - taller door stops?) due 5-21-25
- Bottom of curtainwall is being raised - need to update drawings - dimensions came through on 5-12-25
Need detail for new steel support at bottom of curtain wall
- Detail given to AWS - comments back on 5/27 from AWS - then we can update our shops
Contract mock-up not done - have information from Brad - Ed to work on it
Fin mock-up done - Fin pattern pending CS' RFI deleting holes to fit into shorter fin
Morin panel add to the shop drawings. - Complete
- Project mock-up - need panel fabs for prism - Ed did these - Chris to model them.
Project mock-up Kawneer fabs - Ed is working on this