Notes for the 10/13/26 Meeting
…DELIVERIES…
SEP7- CW Kawneer Misc. material delivery early-Oct(x3 deliveries 1st-3rd week of October)
SEP7- Glazed PW delivery. ETA 11-27
SEP7- Thermazee delivery week of 10/12
2000 Broadwy: Painted flat sheet and a drip week of 10/19
495 Java Kawneer Material mid-Oct
SEP7 - North Clad Material - Pending
BeWell - Kawneer due early November
UCSF-MU - MU is getting shipped on 11/9
…WILSON ITEMS… (*HOT*)
SCB- Need a signed off on a form
Marine: Stamped drawings and calcs by Monday 10/19
Mission: Stamped drawings and calcs by Monday 10/26
SEP 7 Project Calcs- recommendation for the fin hard splice detail
UCSF Benioff - Extrusion approval
UCSF Benioff - Splice joint connections
UCSF Benioff - embeds @ roof level
UCSF Benioff - review Gordon drawings for attachment
UCSF Benioff - Storefront calcs
UCSF Benioff - Attachments to steel
495 Java exterior infill sill anchors (pending Helmy)
UCSF Benioff - Wire mesh calcs
CCSF SSC
Need to install new thresholds @ entries starting from 10/23
SUBS: Troyer
SFO ITB Phase 2 Arrivals
Punch List - STC 55 (beauty cap installation is on-going )
Triage glass swap-out - Central Block - Will be complete by this Thursday 10/15
Full Height Glass swap-out @ door locations
SUBS: GSR
SSF Wellness
Kawneer (1) Door shipping, week of 10/19
Fiber Cement - Site report is sent to XL
Swing Doors - 98% complete (End of October)
Finish Date - By November (goal)
Closeout Submittals
Schedule COR/inefficiencies Review
SUBS: Smith-Emery, Paradise
SC Behavioral
Punchlist issues continue:
CO's ongoing
Warranty date issues with GC - Need to set-up a meeting with Dan
Waterproofing commissioning submittal ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window Film
German Consulate
Phase 2 - Q2 2027
Stage 2 sample submittals required
SUBS: N/A
2000 Broadway
Added Glass door D150A - ETA end of Oct (2 vendors - Action Bullet)
TSS- New replacement glass for storefront
ASAP by will be there to install the two TSS door automation by the week of 10/19- Separate mobilization for Action
Testing #2 - 11/11 (need new dates)
Signed T&M tags (removal of materials) - complete COs
Installing canopy week of - ongoing
SUBS: Smith Emery, ASAP
Stanford Atrium
Interior est. Start Mid. Nov.
Prism - Starts Nov
Panels - Starts Nov
SUBS: USA Scaffold, ASAP
Stanford Public Spaces
Viracon Glass release - Pending RFI (install Oct)
Submittals that are in: Everything for Punch Opening; ordering of Material is Approved as Noted
Getting into Submittals for fire-rated and Glass Film (film installed by CSE)
Anticipated field start in Nov. for (6) Punch Openings
495 JAVA
Interior storefront - Kawneer due in mid-Sept. Doors are Dec
Carvart Glass lead time - field crew FM mid-Oct..
Infill Kawneer material - Due end of Oct
Morin panel install (all locations) - End of Nov
CO work
SUBS: GSR, (Smith Emery - target Nov)
YMCA
NOTICE TO PAUSE ALL WORK- PROJECT IS ON HOLD
Kawneer PO's released - need to release order by 7-31-26
Project pushed for 12 months. Need to create/submit CO for delay
New calculation and potential changes based on new building risk category
UCSF Parking Structure - Benioff
Submittals in process: Gorden revised shop drawing with new attachment details
CSE to submit layout and attachment drawing- We are waiting on Wilson to review attachment questions and extrusion.
Release the new extrusion order- lead time (new count and drawings) - Wilson is reviewing ON HOLD - Pending drawings
Gordon mockup released for fabrication (8/4)
Wire Mesh - Shop drawings out for approval.
Need to submit 12x12 sample
Door shop drawings - TBD
HW list is submitted
Lead time for project panels - 20-24 weeks
SFO Cargo
Pohl Panel Issues - est 5 panels (field-set panels)
Def Sub uploaded 9/29 - tracking when this approval is coming.
Safe Start for GGG needed -pending GGG signature
Kawneer Door - hardware submittal in review
SUBS: Smith Emery
SLAC
FreMarq, AMWP, OLTD, Viracon, and NBK material received. Awaiting structure to be ready for install
Mockup install to start w/o 6/22?
JHA for mock-up work approved. IIPP provided by Karen; has not been submitted
Complete submittals (sunshade & skylight (resubmittal))
Viracon GL-1 glass released 6/5, anticipated arrival at FM w/o 8/3. GL-2 cannot be released until mockup is reviewed by WRNS
SEP7
Northclad Main job shop drawing - waiting on review comments (9/29)
Misc Kawneer materials orders - All 3 orders due by 10/12
Fab Drawings for painted flashing parts, outriggers and fin covers (TBD)
Fabs for misc materials
Safety G&G?
Gilead Interior
TGP released 8/3 - material due early Dec.
Channel Glazing Approved - FM as ready; release material as FM'ing
Kawneer Door Shop - Approved, need FMs to release.
BeWell
Sherwood released - 9/24
Kawneer at shop by mid-Oct. Need Fab drawings
Order GlassFab based on FMs
Door Shop drawings in for review - hardware questions
Horton Slider is approved; waiting on Helmy updates to release.
Interior scope is pending
Ready Access issues - RFI submitted
535 Pacific -Pending