Notes for the 8-4-26 Meeting
…DELIVERIES…
SEP7- CW Kawneer parts -Main job- Week of 8/10
SLAC TC supports (OLTD ctr) - 7/15
CARGO - Steel J's - Due WK Of - 8/10
NORTH CLAD - 8/4 DEL
…WILSON ITEMS… (*HOT*)
SEP 7 Project Calcs
CCSF SSC
Change order items to resolve with XL.
Terrace door installed…working on completing the auto op and actuator
Need to install new thresholds @ entries (awaiting replacement of walk-off mats)
SUBS: Troyer
SFO ITB Phase 2 Arrivals
Punch List - STC 55 (beauty cap - 12 week lead time)
Global Entry Scope - Complete end of Aug.
SUBS: Tintworks, GSR
SSF Wellness
Anticipated Door delivery - Sliders - Ship 8/7- Install Sept
Swing Doors - 98% complete (8/4)
North Glazing - 2 pieces of Glass were the wrong width. Reordered along with New Door Glass and Glass that was scratched - Glass arrived 6/22
Finish Date will be closer to Oct.
SUBS: Smith-Emery, Paradise
SC Behavioral
Paint by Alan Garthwaite and SD is ordered.
Webcor/OLTD is notified of where we stand with touch-up and the sequence of the work scope.
Punchlist issues continue. Initial list complete, additional items being added.
CO's ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window Film
German Consulate
Need to field measure this month and release material
Work “starts” Late Aug 2026
Phase 2 - Q2 2027
Kawneer doors and HW at shop
Need to order glass.
Stage 2 sample submittals required
SUBS: N/A
2000 Broadway
Ballistic door shop drawing is approved - in production
Clear story - being assembled at the shop (8/4)
2nd Kawneer material ETA week of 8/17
Added Glass door - Pending info (8/4)
Testing is scheduled for end of Aug. (clearstory) - Smith Emery
Signed T&M tags (removal of materials) - complete COs
SUBS: Smith Emery
Stanford Atrium
Potential paint issue. TBD (Pittco vs Kawneer)
SUBS: USA Scaffold, ASAP
Stanford Public Spaces
Viracon Glass release - Pending RFI (install Oct)
Submittals that are in: Everything for Punch Opening Ordering of Material is Approved as Noted
Getting into Submittals for fire-rated and Glass Film
Anticipated field start in Sept. for (6) Punch Openings
495 JAVA
Brad reviewing pricing for entry door
Morin Panel install complete mid-SEPT
Parapet modifications (COR) starting 5/13 - ongoing
Interior storefront - Kawneer due in mid-Sept.
Carvart Glass lead time - field crew FM mid Aug
Kawneer Doors due in mid-Nov
Ongoing change orders request.
SUBS: Tint Works, Smith Emery
YMCA
NOTICE TO PAUSE ALL WORK- PROJECT IS ON HOLD
Kawneer PO's released - need to release order by 7-31-26
Project pushed for 12 months. Need to create/submit CO for delay
New calculation and potential changes based on new building risk category
UCSF Parking Structure
Submittals in process
Release the new extrusion order- lead time (new count and drawings)
Gordon mockup released for fabrication (8/4)
Gordon Project Shops - resubmittal - due wk of 8/10
Wire Mesh - submittal/review
Lead time project panels - 20-24 weeks
SFO Cargo
WAREHOUSE GLASS - due last wk of Aug
Glazed in panels (Pohl) due from Linetec - 8/13. Phase 2 - TBD.
Soffit Panels - being made by shop - painting at Cert. Ena.
Fremarq project material: 2-4 truckloads by 8/17 requested -Pending Clark conf. When we can del. to site.
Multiple outstanding Fremarq Questions
COR review - Backup collection
Safe Start for GGG needed - review Bo
SUBS: Smith Emery
SLAC
FreMarq, AMWP, OLTD, Viracon, and NBK material received. Awaiting structure to be ready for install
Mockup install to start w/o 6/22?
JHA for mock-up work approved. IIPP provided by Karen, has not been submitted
Complete submittals (sunshade & skylight (resubmittal))
Viracon GL-1 glass released 6/5, anticipated arrival at FM w/o 8/3. GL-2 cannot be released until mockup is reviewed by WRNS
SEP7
Gordon fins- finishing by LineTec- ETA shop: Week of 8/10
Northclad Main job shop drawing - in review by Helmy
Revise CO's with updated shop labor
Mockup panels - arrived
Kawneer - arrives mid/end of Aug.
Misc Kawneer materials - need to submit to Kawneer for SL takeoff.
Gilead Interior
TGP released 8/3 - material due early Nov.
Channel Glazing - R&R sitting with Helmy
Kawneer Shop - R&R sitting with Kawneer. sent to Kawneer 8/3