Notes for the 5-26-26 Meeting
…DELIVERIES…
Cargo MU material from FreMarq 6/15ish
Sep7 MU NorthClad Mis. parts and accessories week of 6/15
Sep7 MU Kawneer material week of 6/15
Sep7 MU Painted flashing and Outriggers from AMWP- Week of 6/15
SLAC TC supports (OLTD ctr) - 7/15
CCSF SSC
Change order items to resolve with XL.
Terrace door installed…working on completing the auto op and actuator
Need to install new thresholds @ entries (awaiting replacement of walk-off mats)
SUBS: Troyer
SFO ITB Phase 2 Arrivals
COR's from Brad - Only have Bulletin COR's to submit
SUBS: Tintworks, GSR
BCC Milvia
Waiting for SCO approvals
SUBS: Paradise ; Smith-Emery
SSF Wellness
Anticipated Door delivery - Sliders - June - Install Mid June
Swing Doors - At Paradise Shop - Glass is at the shop - Install Mid June
Paradise to update on new door - Old one is too short… Still waiting on Julio for Information
Field de-glaze and re-glaze for West Level 1, Timber CW. -
North Glazing - 2 pieces of Glass were the wrong width. Reordered along with New Door Glass and Glass that was scratched
Finish Date will be closer to September
SUBS: Smith-Emery, Paradise
SC Behavioral
Touch-up by Alan Garthwaite and SD completed and approved.
Webcor/OLTD is notified of where we stand with touch-up and the sequence of the work scope.
Punchlist and PCI work completed. There will be a few additional items and a CO work by adding a trim at Tower
CO's ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window Film
German Consulate
Need to field measure this month and release material
Work “starts” July of 2026
Phase 2 - q2 2027
Kawneer doors and HW at shop
Need to order glass.
Stage 2 sample submittals required
SUBS: N/A
2000 Broadway
Phase 1, removing panels and storage- completed.
Added scope (Phase 2), removing additional panels
Ballistic door shop drawing is out for approval
clear story glass is delivered
Kawneer material ETA week of 7/20
signed T&M tags (removal of materials) - complete COs
Stanford Atrium
SUBS: USA Scaffold, ASAP
Stanford Public Spaces
Submittals that are in: Everything for Punch Opening Ordering of Material is Approved as Noted
Getting into Submittals for Fire Rated and Glass Film
Anticipated field start in Sept. for (6) Punch Openings
495 JAVA
Pricing:
Morin Panel install complete mid-June
Parapet modifications (COR) starting 5/13
Waiting on Kawneer pricing, drawings approved.
SUBS: Tint Works, Smith Emery
YMCA
Kawneer PO's released - need to release order by 7-31-26
Project pushed for 12 months. Need to create/submit CO for delay
New calculation and potential changes based on new building risk category
UCSF Parking Structure
Submittals in process
Gordon mockup drawings - due 6/19
Mockup production - 8-10 weeks (requested an improvement)
Gordon Project Shops - due 7/24
leadtime project panels - 20-24 weeks
SFO Cargo
Glass released (pending warehouse glass) - arrives mid to late July
Glazed in panels (Pohl) released - due to Fremarq mid July
Soffit Panels - release by 8/1
Fremarq project material: 2-4 truckloads by 8/17 requested
Multiple outstanding Fremarq Questions
City Build - Labor requirements
SLAC
FreMarq, AMWP, OLTD, Viracon, and NBK material received. Awaiting structure to be ready for install
Mockup install to start w/o 6/22?
JHA for mock-up work approved. IIPP provided by Karen, has not been submitted
Complete submittals (Sunshade, & skylight (resubmittal))
Viracon GL-1 glass released 6/5, anticipated arrival at FM w/o 8/3. GL-2 cannot be released until mockup is reviewed by WRNS
SEP7
Submittal process started.
MU glass received
Kawneer profile expected by the week of 6/15 (2 deliveries)
Gordon fins- ETA week of 7/20 (date is still pending)
Northclad fabs revised pending Helmy's review and release. ETA 4 weeks after release (anticipating release week of 6/15)
MU steel is installed
When is framing ready for layout?
Order Kawneer material - by 6/20
Gilead Interior
TGP drawings submitted 6/9
CSE is working on channel glazing Shops (week of 6/15)
Kawneer Shops due 6/19