Notes for the 4-14-26 Meeting
…DELIVERIES…
SSF Wellness - Fundermax (Extra Sheets) - 3/6 Ship Date from Austria
UCSF - Gordon (internal mockup) ships week of 4/14
SSF Wellness - Week of 4/13: SHApe ACM extra panel sheets and misc parts for fabrication and Field Install
SFO ITB - In Transit Lounge - SSTL Base Panels ; Coming from Pohl
SLAC MU - OLTD subgirts airfreight 4/10
SLAC MU - FreMarq units (TBD)
CCSF - 4 manual closers (Access) (WO 4/13)
CCSF SSC
Change order items to resolve with XL.
Terrace door installed…working on completing the auto op and actuators
Need Troyers recommendation on what to do with power assist/auto op. for manual doors at entry
Need to install new thresholds @ entries (awaiting replacement of walk off mats)
SUBS: Troyer
SFO ITB Phase 2 Arrivals
Scopes starting to Ramp Up:
- In Transit Lounge Wall: Base Panel Install; Waiting on Pohl… Forming this week 4/14/26
- Custom Film to be performed by Tintworks and Film will ship 4/17 to shop
Need to work with Brad on COR’s - HOT
SUBS: Tintworks
BCC Milvia
Shade trims- CO Work starting 4/14 to 4/17
Punch list work: Resuming 4/14 to 4/17
CO's on-going
SUBS: Paradise ; Smith-Emery
SSF Wellness
Anticipated Door delivery - Sliders - April,
Swing Doors - At Paradise Shop - Glass is at shop
Field de-glaze and re-glaze for West Level 1, Timber CW. - Waiting for North to open up and we will perform work on North and West
Refabrication of a few Fundermax Panels. Extra Sheets set to ship from Austria 3/6
Schedule was updated and sent over to XL, Shows CSE finishing Exterior in August.
Interior TBD
Man Power needs a closer look with Bo.
SUBS: Smith-Emery, Paradise
SC Behavioral
Touch-up by Stuart Dean: new paint sample is applied. Pending the design team/owner review.
Touch-up by Alan Garthwaite is expected this week and sample is scheduled for this Friday 4/17.
Webcor/OLTD is notified of where we stand with touch-up and the sequence of the work scope.
ACD 196 for the South 5 tile subgirt / Expansion joint installation is completed.
SI#RFI 2346-SITE-PS2 Privacy Screen Gap Coverage- installation completed
Erst breezway gate installation will be completed this week
Punchlist and PCI work on going, expected completion end of the month
CO's ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window Film
German Consulate
Need to field measure this month and release material
Work “starts” July of 2026
Phase 2 - q2 2027
Kawneer doors and HW at shop
Need to order glass.
Stage 2 sample submittals required
SUBS: N/A
San Quentin RC
Punch List Items - Complete 2/20
Stuart Dean - paint to be done by end of March
SUBS: Paradise, Smith-Emery
2000 Broadway
Phase 1, removing panels and storage- completed.
Added scope (Phase 2) Removing additional panels
Ballistic door shop drawing submitted, Product data submittal completed
Submittals approved. Pending lower side U-channel black finish approval
Kawneer material release in process
On-site in April for reinstall of walls/panels
Stanford Atrium
SUBS: USA Scaffold, ASAP
Stanford Public Spaces
Submittals that are in: Kawneer Frame Color Samples, Joint Sealant Color Samples, and Glass Samples
Getting into Submittals for Fire Rated and Glass Film
495 JAVA
Waiting to install L1 demo scope. (Pending Painter)
Morin panel received, work to start in April
Alternate for additional 4-5 opening (and reinstall) has been accepted
SUBS: Tint Works, Smith Emery
YMCA
Kawneer PO's released - need to release order by 7-31-26
Project pushed for 12 months.
Kawneer package submittal submitted
Glass submittal and samples submitted.
UCSF Parking Structure
Submittals in process
Gordon meeting last week - engineer proposing using a larger attachment clip to accommodate 3/8" gap. Need to determine if we are proceeding with their “modified” system. Internal mock up to check if tolerances will work ships 4/6
SFO Cargo
Released Viracon & Fremarq on PMU (for office). Still need to finalize the Warehouse for release.
Submittals
SLAC
FreMarq, OLTD, Viracon, and NBK released on mock-up.
AMWP released for parapet caps/panels for MU (due by 5/6)
BHJ - released for flashing on MU (due 4/20)
Mockup install to start w/o 4/27 with our work likely to begin 5/4. Need to schedule onsite preinstallation conference with DOME, CSE, PCI Etc. for mockup sequence/installation
JHA for mock-up work approved. Need to complete remaining safety docs
Complete submittals (Sunshade, skylight (resubmittal), as well as remaining PD - Insulation, membrane, sealants, etc.)
SEP7
Submittal process started.
Glass samples expected in the week of 4/13
Mockup shop drawings submitted
MU glass released
Kawneer profile release in works
Gordon Die drawing is approved. Getting revised material quote
LineTech is updating the quote
Northclad is released with working on MU fab drawings. Waiting on metal panel Bronze color approval
Gilead Interior
Need on-boarding deliverables
Starting submittals