Notes for the 2-3-26 Meeting
…DELIVERIES…
SCB- B/O Tower Coping panel (AMWP) ETA 2/6
SFO ITB - McGrory replacement Glass - Ship Date 2/6/26
CCSF SSC
Meeting 2/4 with XL, Kitchell & CSE to discuss open punchlist items
Change order items to resolve with XL.
Terrace door installed….need to schedule meeting due to auto op issues including electrician work that needs to be completed
New thresholds priced, as well as power assist option at other entry doors - awaiting direction from XL on whether to proceed.
SUBS: Troyer
SFO ITB Phase 2 Arrivals
Feature Wall Glass Install - 1 Replacement lite left
Scopes starting to Ramp Up:
- In Transit Lounge Wall: Fabrication Drawings are in fabricators court
Need to work with Brad on COR’s - HOT
GGG scope of work for onsite labor
SUBS: Tintworks
BCC Milvia
Balcony coping panels and installing balcony glass. completed. L4 requires a new longer fitting and expected by 2/6
Punch list work: Schedule for unit removal due to PT and broken glass is approved. CSE to provide lift and swing stage, XL to provide Crane
CP's on-going
SUBS: Paradise ; Smith-Emery
Congregation Emanu-El
Items to complete:
Door Go Backs
Stuart Dean Oil Rubbed door rails
SUBS: Smith-Emery, ASAP
SSF Wellness
Door - Horton Color Samples (Paradise) - Paint Samples are at Shop. To confirm with Gabe for release. Doors will be going in around April/May
Anticipated Door delivery - Sliders - April,
Swing Doors - At Paradise Shop
Field de-glaze and re-glaze for West Level 1, Timber CW.
Engineering to provide clip layout drawing for shop to add clips on Fundermax Panels
Refabrication of a few Fundermax Panels. Working on ordering extra sheet.
SUBS: Smith-Emery, Paradise
San Mateo Med Center
Talked to Jeff with Truebeck about COs, most approved. He told me Paul will be calling this week to discuss escalation.
Misc punchlist to be addressed in early Jan (Bo)
SUBS: Paradise, Tintworks
SC Behavioral
OLTD MP-1 for columns on hold for owners sign-off for insulation
Centria panel installation to be completed as soon as remaining coping panels are delivered by AMWP
Touch-up by Stuart Dean: new paint is ordered and expected in the week of 2/9 to resume the work
Webcor/OLTD is notified of where we stand with touch-up and the sequence of the work scope.
Panels @ gates between garage/bldg ,resuming the work from 2/6 and will be finished by next week
Skybridge soffit panels removed and insulation installed. Installation in progress.
ACD 196 for the South 5 tile subgirt / Expansion joint to be submitted waiting for approval
SI#RFI 2346-SITE-PS2 Privacy Screen Gap Coverage- submitted. Received confirmation to proceed with installation
PS2 - infill panels to be installed, Material received. Starting after gates in the week of 2/9
CO's ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window FIlm
German Consulate
Work starts summer of 2026
Kawneer doors and HW at shop
Need to order glass.
Stage 2 sample submittals required
SUBS: N/A
San Quentin RC
Punch List Items - Complete 2/17
Canopy Repairs - Complete 2/17
Water Testing (2/4-2/5) - Last round
SUBS: Paradise, Smith-Emery
2000 Broadway
Phase 1, removing panels and storage- completed.
Added scope (Phase 2) Removing panels between grid 4 and 5 on 8/2. Done
3 Doors that are getting added. Rom is sent.
On-site in April for reinstall of walls/panels
Stanford Atrium
Pittco doors were received by the shop 2.3.26
ASAP has components at shop and I need to coordinate the subframing with ASAP. Who is responsible for subframe fabrication. ASAP or CSE?
SUBS: USA Scaffold, ASAP
495 JAVA
Exterior Storefront Submittal needed.
SUBS: Tint Works, Smith Emery
YMCA
Kawneer PO's released - need to release order by 7-31-26
Paul to start working on submittal packages.
UCSF Parking Structure
Submittal list needs to be developed
Gordon meeting last week - engineer proposing using a larger attachment clip to accommodate 3/8" gap. Need to determine if we are proceeding with their “modified” system
SFO Cargo
SLAC
SEP7
Gilead Interior