Notes for the 12/16/25 Meeting
…DELIVERIES…
Shop closed - 11-26 to 11-28, and 12-22 to 1-2
Milvia- Balcony Coping ETA TBD from AMWP
SFO- Mcgory: 3rd shipment arriving 12/17
SFO ITB - SS panel from Pohl, base panels due to arrive next week, need to coordinate with Pohl/shop
Stanford Atrium - Viracon glass ships 1/5
SSF Wellness - OLTD new replacement material due at SFO 12/24
SCB - coping panels remakes (tower) & PS2 gap filler (AMWP) - look into delivering direct to the jobsite
Bechtel
Close out docs - complete
Change order finalization w/ XL
SUBS: Paradise, Stuart Dean
Stanford GSE
Door repair (Paradise)
Need final answer from MCB to confirm all punch is complete
SUBS: Intertek, Paradise, Tintworks
CCSF SSC
Change order items to resolve with XL.
Paradise to help with auto op install at door 2001, may need electrician to complete work prior to them coming onsite.
Need to replace L2 door (height issue) , released to Kawneer. Doors received. Scheduled replacement 12/22
Glass for door due week of 12/15
New thresholds priced, as well as power assist option at other entry doors - awaiting direction from XL on whether to proceed.
Closeout docs - revise date (need new warranties from suppliers)
SUBS: Troyer
SFO ITB Phase 2 Arrivals
Feature Wall Glass Install - Phase 4 (1st Wall) Mid a November, glass in Dec ; Phase 5 (2nd Wall) in February.
Shop drawings - Completed ; Gensler to review and anticipate revisions per coordination meetings in future
Need to work with Brad on COR’s
GGG scope of work for onsite labor
SUBS: Tintworks
BCC Milvia
Doors installed, auto ops being installed this week
Replacement glass -G5 unit and broken replacement arrived but not installed yet
Delivery of units for installation started: #G4: Installed, Next: #1: G1(installed), G2(installed), G3(installed), G10(installed), G5(installed), G7(installed), G9(installed), G11(installed), Balcony(Installed)& Roof CW(Installed). Roof and L6 coping panel and waterproofing.
SUBS: Paradise ; Smith-Emery
Congregation Emanu-El
Items to complete:
Blumcraft Door: replacement glass/rails expect to receive soon, install in January (need Stuart Dean to oil rub the rails)
SUBS: Smith-Emery, ASAP
SSF Wellness
Door Submittals (Paradise) - Released, coordination of wiring etc. completed, a few RFI's to be finalized.
Anticipated material delivery - Sliders - Feb, All other doors in Jan.
Fundermax, FCP material - arrived-
Engineering to provide clip layout drawing for shop to add clips
SUBS: Smith-Emery, Paradise
San Mateo Med Center
Talked to Jeff with Truebeck about COs, most approved. He told me Paul will be calling this week to discuss escalation.
Misc punchlist to be addressed in early Jan (Bo)
SUBS: Paradise, Tintworks
SC Behavioral
Elward/Centria panel installation started to be completed by end of the month.
Touch-up by Stuart Dean, material ordered on 11/14 (lead time x4 weeks). Expecting start date week of 12/15.
Need PPG report to determine next steps on potential paint variation. Marked panels that they believe are acceptable vs those that should be repainted.
Panels @ gates between garage/bldg (TBD)
PS2 - infill panels to be installed
Skybridge soffit panels currently being installed
ACD 193 to be submitted
Revise/submit drawing for new expansion joint location below bridge
CO's ongoing
SUBS: ASAP, Bigge, Stuart Dean, American Window FIlm
German Consulate
Work starts summer of 2026
Kawneer doors and HW at shop
Need to order glass.
Stage 2 sample submittals required
SUBS: N/A
San Quentin RC
Doors installed and ongoing should be complete 12/19
Canopies & doghouses to be complete by 12/4
Bldg. D - Kawneer here ; Glass to go. January Install.
SE water testing 1/5 & 1/6 (1 chamber, balance of nozzle tests)
Deglaze testing need schedule developed
SBE documentation required. good as of 9/8/25
SUBS: Paradise, Smith-Emery
2000 Broadway
Paul is running this one
Phase 1, removing panels and storage- completed.
Added scope (Phase 2) Removing panels between grid 4 and 5 on 8/2. Done
3 Doors that are getting added. Rom is sent.
Stanford Atrium
Pittco and ASAP released- Should be getting doors by Mid. December
Shop to fab/install SS brackets for fins
SUBS: USA Scaffold, ASAP
495 JAVA
Shop drawings needed for exterior elevation to include new door locations
Panel approval (morin), need to determine who is drawing the panel scope (CSE or Morin)
Need to develop interior shop drawings
SUBS: Tint Works, Smith Emery
YMCA
Kawneer PO's released - need to release order by 7-31-26
Paul to start working on submittal packages.